FAA Design/Build En-Route Modernization Project

Primarily a mechanical system and equipment upgrade project, the The San Juan CERAP counted on LORD for the a major mechanical sustainment  upgrade, including associated HVAC mechanical controls and electrical equipment supply and instalaltion.

Lord's Scope Inlcuded:

  • ALL WORK TO BE PERFOMED ON A 24 HOURS OPERATING FACILITY WITH ZERO INTERRUPTIONS TO HVAC OR ELECTRICAL SERVICE
  • architectural components to support mechanical Chiller/Cooling Tower work.
  • Smoke and fire stopping of pre‐existing and new penetrations.
  • Patching and repairing of architectural finishes.
  • New enclosed space new Electrical MCC.
  • Installation, Operation and Maintenance of a Temporary Chiller Plant.
  • Rellocation of all electrical services feeding to existing - temporary - and new Chiller Plant.
  • Existing air‐handling units removed and new air‐handling units installed.
  • Existing refrigerant monitoring system replaced with new.
  • Existing HVAC Mechanical pneumatic controls on existing air‐handing units removed and replaced with new Andover Controls DDCsystem.
Category: